Sr.
No. |
Name of Work |
Estimated cost (Rs. Lakh) |
Amount put to Tender Rs. in Lakhs |
Name of contractor |
Date of work order |
Position of work |
1. |
Amravati-Badnera Minibypass from Biyani Square to Chaprashipura to Frezarpura including
Improvement to Biyani Square. |
239.42
+40.00 |
212.36 |
M/s Jaswantsingh Oberoy, Yeotamal |
04.12.03 |
Work In Progress |
2. |
Minibypass from Frezarpura to Yashoda Nagar including Improvement to Dastur Nagar
Square. |
219.35
+40.00 |
231.31 |
M/s D.H. Khandelwal and G.H. Khandelwal Joint Venture, Amravati |
08.12.03 |
Work In Progress |
3. |
Amravati Chandur Railway road Maal Tekadi to mini bypass including Improvement to
Chaparashipura Square. |
295.00
+40.00 |
123.50 |
M/S S.L. Malani, Murtizapur. |
09.12.03 |
Work In Progress |
4. |
Part Railway station to S.T. Stand to Maaltekadi |
164.93 |
150.98 |
M/s D.C. Gurubaxani, Nagpur. |
04.12.03 |
Work In Progress |
5. |
a) |
Malviya chowk to Chitra Square |
55.92 |
46.63 |
M/s Sanjay Construction Industries Paratwada |
08.12.03 |
Work In Progress |
b) |
Irvin Chowk to Railway Station |
73.96 |
59.89 |
6. |
Amravati Achalapur Road |
168.71 |
152.23 |
M/s P.M.A. Constructions Nagpur |
04.12.03 |
Work In Progress |
a) |
Improvement to Road from Nagpuri gate to Asoria Petrol Pump & |
b) |
Improvement to Road from Asoria Petrole pump to Jamil colony to Truck Terminal |
7. |
Improvement to Road from Panchawati square to Gadge Nagar, Shegao naka toKathgora
naka and improvement to Shegaon Naka |
285.86 +38.8 |
253.00 |
M/s Phonix Engineers Nagpur |
04.12.03 |
Work In Progress |
8. |
Improvement of Road from Rajapeth Railway crossing to Dastur nagar chowk to Chatri
talao |
168.68 |
156.07 |
M/s G. H Khandelwal & D.H. Khandelwal (JV), Amravati. |
08.12.03 |
Work In Progress |
9. |
Improvement of Road fromOld Cotton market to Shegaon to Rahatgaon |
184.94 |
166.07 |
M/s Siddharth General agencies and Budhalani Builders Amravati |
04.12.03 |
Work In Progress |
10. |
Improvement of Road from Collector office to Chaparashipura |
109.44 |
101.00 |
M/s Green earth Asphalt and Power Private Limited, Achalpur |
16.12.03 |
Work In Progress |
11. |
Improvement of Road from Gandhi Chowk to Mukbadhir vidyalaya |
202.05 |
187.01 |
M/s S. L. Malani Murtizapur |
09.12.03 |
Work In Progress |
12. |
Improvement of Road fromGandhi chowk to Deeparchan |
43.58 |
39.98 |
13. |
Improvement of Road from New Cotton market to Valgaon |
38.46 |
35.36 |
M/s Abdul Rafique and D.H. Khandelwal, J.V. Amravati. |
09.12.03 |
Work Completed |
14. |
Improvement of Road from Survey No 1 to 121 Mauza Navsari |
20.32 |
19.73 |
15. |
Improvement of Road from Maal tekadi to Pharasi stop via Rajendra Colony |
108.29 |
99.01 |
M.B.Sheikh and D.H. Khandelwal, J.V. Amravati. |
09.12.03 |
|
16. |
Improvement of Road fromPachawati square to Maal tekadi Road |
99.04 |
93.81 |
M/s Ajaykumar Heda & S.L. Malani. J.V. Murtizapur |
10.12.03 |
Work In Progress |
17 |
Improvement to Road from Takhatmal to Yashoda Nagar Square. |
42.14 |
37.48 |
M/s. Laxmi Civil Engineering Services Pvt. Ltd. Kolhapur |
04.08.04 |
Work In Progress |
18 |
Improvement to Road from Railway Station Square to Tapar Hostel. |
56.43 |
49.02 |