IRDP Amravati

Introduction

The Government of Maharashtra approved Amravati City Integrated Road Development Project on dated 14/02/02 for Rs. 114.47 Crore and declared M.S.R.D.C. Ltd. as an "Entrepreneur" for the Project.

The M.S.R.D.C. Ltd. Decided to execute the Project partly through Public Works Department and Amravti Municipal Corporation & P.M.C. appointed by M.S.R.D.C

As per G.R. Following Works are Included in the Project

Sr.No. Name of work Nos/Length Cost in crores
1. ROB 2 10.00
a) Widening of existing R.O.B.at Badnera
b) R.O.B. At Mini Byepass
2. RUB 2 5.00
a) At Rajapeth
b) At Navathe Plot
3. Flyover bridge 2 15.00
a) At Sham and Rajkamal Square
b) At Jaistambha Square
4. Byepass on western side of Amravati City (Akoli Byepass) 16.30 kms 20.00
5. Roads under jurisdiction of P.W.D. 16 Nos/16.95 Kms 20.00
6. Roads under jurisdiction of A.M.C. 20 Nos./70.30 Kms 15.00
7. Development of Squares 15 5.00
1) P.W.D. 12 No
2) A.M.C. 3 Nos
8. Toll Booths. 8 5.00
9. Shifting of utility, 3 % Contingecies, 3% for shifting of poles (100% expenditure) except improvement to System 5.70
10. M.S.R.D.C. EXPENDITURE 10 % 10.07
11. Expenditure of bridges on Amravati Badnera road 3.70
Total 114.47
MSRDC - Project - Amravati City Integrated Road Development Project
MSRDC - Project - Amravati City Integrated Road Development Project

M.S.R.D.C. has Sanctioned Following Works

Sr.No. Type of Work Implementing Agency Number Cost Rs. Crore)
1. Improvement to Square P.W.D. 12 5.22
2. Improvement to Square A.M.C. 03 0.90
3. Improvement to Road P.W.D. 17 19.31
4. Improvement to Road A.M.C. 14 14.99
5. Electrical Utility P.W.D. A.M.C. -- 5.70
6. Byepass on western side of Amravati City (Akoli Byepass) M.S.R.D.C. 1
(18.30 Km.)
20.00
7. Construction of Flyovers M.S.R.D.C. 2 15.00
8. Widening of bridges on Amravati Badnera road M.S.R.D.C. 1 job 3.70
Total 84.82
MSRDC - Project - Amravati City Integrated Road Development
        Project
MSRDC - Project - Amravati City Integrated Road Development
        Project

Current Position of Sanctioned Works

Sr.
No.
Type of work Implementing Agency Total No. of works Works completed Works in Progress
No. Cost (Rs. in Crore) No. Cost (Rs. in Crore) No. Cost (Rs. in Crore)
1. Improvement to Square P.W.D. 12 5.22 7 3.17 -- --
A.M.C. 03 0.90 3 0.90 -- --
M.S.R.D.C. -- -- -- -- 5 2.05
2. Improvement to Road P.W.D. 16 19.31 9 4.25 -- --
A.M.C. 14 14.99 3 4.25 -- --
M.S.R.D.C. -- -- 17 24.81 2 0.99
3. Shifting of Electrical Utility P.W.D. 1 Job 5.70 1 Job 5.70 -- --
A.M.C. -- --
M.S.R.D.C.
4. Akoli Bypass M.S.R.D.C. 1 20.00 -- -- 1 20.00
5. Construction of Flyovers M.S.R.D.C. 2 15.00 -- -- 2 15.00
6. Widening of bridges on Amravati Badnera road M.S.R.D.C. 1 job 3.70 1 job 3.70 -- --
Total 47 66.12 24 21.97 26 62.85
MSRDC - Project - Amravati City Integrated Road Development
        Project
MSRDC - Project - Amravati City Integrated Road Development
        Project

Position of Works Under P.W.D. Amravati

Sr.
No.
Name of Work Estimated cost (Rs. Lakh) Amount put to Tender Rs. in Lakhs Name of contractor Date of work order Position of work
Road Improvement
1. Nagpur-Amravati-Akola Road
1) Panchawati Square to Irvin Square 122.75 77.71 M/S D.H. Khandelwal Amravati 26.03.03 Work Completed
2) Improvement to Irvin Square to Malviya Square Included in square Improvement M/S D.C. Gurubaxani, Nagpur 25.03.03 Work Completed
3) Improvement to Malviya to Jaistambha square
4) Improvement from Jaistambha square to Shamchowk
5) Improvement from Sham Chowk to Rajkamal Chowk
6) Improvement from Rajkamal Chowk to Rajapeth Chowk
7) Improvement from Rajapeth Chowk To Navathe Plot 191.83 109.54 M/s S. L. Malani, Murtizapur. 25.03.03 Work Completed
2. Improvement to Amravati Achalpur Road Part Jaistambha to Tanga stand Tanga Stand to Asoria Petrol Pump to Nagpuri Gate. 113.40 103.84 M/s P.M.A. Constructions, Nagpur 25.03.03 Work Completed
Total 8 Roads 427.98 291.09
Square Improvement
1. Improvement to Power house Square 46.81 30.00 M/S D.H. Khandelwal Amravati 26.03.03 Work Completed
2. Improvement to Irvin Square 63.36 31.1 M/S D.C. Gurubaxani, Nagpur 25.03.03 Work Completed
3. Improvement to Malviya Square 48.24 30.52
4. Improvement to Jaistambha Square 49.34 34.0
5. Improvement to Sham and Rajkamal Square 42.39 30.67
6. Improvement to Rajapeth Square 26.66 14.35
7. Improvement to Nagpuri Gate Square 40.00 38.74 M/s P.M.A. Const-ructions, Nagpur 25.03.03 Work Completed
Total 7 Square 316.80 209.38

Information of Works in Progress under Amravati Municipal Corporation

Sr.
No.
Name of Work Estimated cost (Rs. Lakh) Amount put to Tender Rs. in Lakhs Name of contractor Date of work order Position of work
Road Improvement
1. Irvin to Biyani College 137.91 129.78 M/s D.H. Khandelwal, Amravati 26.03.03 Work Completed
2. Approach Road to Badnera Railway Station 39.95 38.50 M/s Green earth Asphalt and Power Private Limited, Achalpur. 23.04.03 Work Completed
3. Railway Bridge to Congress Nagar 247.39 230.58 M/s Sanjay Construction Industries, Paratwada 04.08.03 Work Completed
Total 3 Roads 425.25 398.86
Square Improvement
1. Girls High School Square 39.66 36.76 M/s D.H. Khandelwal, Amravati 26.03.03 Work Completed
2. Court Square 26.72 24.84
3. Rukmini Nagar Square 23.62 06.66 M/s Sanjay Const-ruction Industries, Paratwada 04.08.03 Work Completed
Total 3 Squares 90.00 68.26

M.S.R.D.C. has appointed M/s Consulting Engineering Services, New Delhi as P.M.C. for the following Works from 23.12.03 & the Work Orders have been given for these Works under M.S.R.D.C.

Sr.
No.
Name of Work Estimated cost (Rs. Lakh) Amount put to Tender Rs. in Lakhs Name of contractor Date of work order Position of work
1. Amravati-Badnera Minibypass from Biyani Square to Chaprashipura to Frezarpura including Improvement to Biyani Square. 239.42
+40.00
212.36 M/s Jaswantsingh Oberoy, Yeotamal 04.12.03 Work In Progress
2. Minibypass from Frezarpura to Yashoda Nagar including Improvement to Dastur Nagar Square. 219.35
+40.00
231.31 M/s D.H. Khandelwal and G.H. Khandelwal Joint Venture, Amravati 08.12.03 Work In Progress
3. Amravati Chandur Railway road Maal Tekadi to mini bypass including Improvement to Chaparashipura Square. 295.00
+40.00
123.50 M/S S.L. Malani, Murtizapur. 09.12.03 Work In Progress
4. Part Railway station to S.T. Stand to Maaltekadi 164.93 150.98 M/s D.C. Gurubaxani, Nagpur. 04.12.03 Work In Progress
5. a) Malviya chowk to Chitra Square 55.92 46.63 M/s Sanjay Construction Industries Paratwada 08.12.03 Work In Progress
b) Irvin Chowk to Railway Station 73.96 59.89
6. Amravati Achalapur Road 168.71 152.23 M/s P.M.A. Constructions Nagpur 04.12.03 Work In Progress
a) Improvement to Road from Nagpuri gate to Asoria Petrol Pump &
b) Improvement to Road from Asoria Petrole pump to Jamil colony to Truck Terminal
7. Improvement to Road from Panchawati square to Gadge Nagar, Shegao naka toKathgora naka and improvement to Shegaon Naka 285.86 +38.8 253.00 M/s Phonix Engineers Nagpur 04.12.03 Work In Progress
8. Improvement of Road from Rajapeth Railway crossing to Dastur nagar chowk to Chatri talao 168.68 156.07 M/s G. H Khandelwal & D.H. Khandelwal (JV), Amravati. 08.12.03 Work In Progress
9. Improvement of Road fromOld Cotton market to Shegaon to Rahatgaon 184.94 166.07 M/s Siddharth General agencies and Budhalani Builders Amravati 04.12.03 Work In Progress
10. Improvement of Road from Collector office to Chaparashipura 109.44 101.00 M/s Green earth Asphalt and Power Private Limited, Achalpur   16.12.03 Work In Progress
11. Improvement of Road from Gandhi Chowk to Mukbadhir vidyalaya 202.05 187.01 M/s S. L. Malani Murtizapur 09.12.03 Work In Progress
12. Improvement of Road fromGandhi chowk to Deeparchan 43.58 39.98
13. Improvement of Road from New Cotton market to Valgaon 38.46 35.36 M/s Abdul Rafique and D.H. Khandelwal, J.V. Amravati.  09.12.03 Work Completed
14. Improvement of Road from Survey No 1 to 121 Mauza Navsari 20.32 19.73
15. Improvement of Road from Maal tekadi to Pharasi stop via Rajendra Colony 108.29 99.01 M.B.Sheikh and D.H. Khandelwal, J.V. Amravati. 09.12.03
16. Improvement of Road fromPachawati square to Maal tekadi Road 99.04 93.81 M/s Ajaykumar Heda & S.L. Malani. J.V. Murtizapur 10.12.03 Work In Progress
17 Improvement to Road from Takhatmal to Yashoda Nagar Square. 42.14 37.48 M/s. Laxmi Civil Engineering Services Pvt. Ltd. Kolhapur 04.08.04 Work In Progress
18 Improvement to Road from Railway Station Square to Tapar Hostel. 56.43 49.02

Works in Progress of Shifting of Electrical Utility

Sr.No. Name of Work Estimated cost (Rs. Lakh) Amount put to Tender (Rs. in Lakhs) Name of contractor Date of work order Position of work
Works under P.W.D. Amravati.
1. Panchawati to Malviya Square (National Highway No.6) 72.023 57.719 M/s Digitronix Equipment, Nagpur. 16.10.03 Work completed.
2. Malviya Square to Nawathe (National Highway No.6) 153.636 153.482 M/s Shalaka Electric, Pune. 09.10.03 Work completed.
3. Railway Overbridge, Jaistambha Chitra to Nagpuri gate (State Highway No.6) 62.670 50.224 M/s Omicron Engineer, Aurangabad 24.09.03 Work completed.
Works under A.M.C. Amravati.
1. Irvin to Biyani Square 98.462 79.971 M/s Top Electricals, Thane. 28.10.03 Work completed.
2. Railway Bridge to Congress Nagar 78.465 67.838 M/s Omicron Engineer, Aurangabad 15.10.03 Work completed.
3. Approach Road to Badnera Railway Station 31.285 30.508 M/s Wish-on Enterprises, Thane 16.10.03 Work completed.
Works under M.S.R.D.C.
On various 18 Roads 520.00 678.51 M/s. Shaktikumar M. Sancheti Ltd. Nagpur 15.04.05 Work completed.

Position of Work of Providing Street Light

Sr.
No.
Name of Work Estimated cost (Rs. Lakh) Amount put to Tender Rs. in Lakhs Name of contractor Date of work order Position of work
1. Providing one Highmast Light and Street Lights on Panchavati, Irvin, Rajkamal, Rajapeth to Navathe and on Railway Over Bridge, Jaistambh, Chitra to Nagpuri Gate 125.66 123.06 M/s Omicron Engineers, Aurangabad 20.05.04 Work completed.

Position of Construction of Akoli Bypass

Sr.
No.
Name of Work Estimated cost (Rs. Lakh) Amount put to Tender Rs. in Lakhs Name of contractor Date of work order Position of work
1. Construction of Akoli Bypass Scope :
Road – 18.30 km.
C.D. work – 27No.
Box cell/
Minor Bridge–14No.
Major Bridge–1No.
2000.00 1598.00 M/s Pratibha Construction Engineers Contractors (I) Pvt. Ltd. Kolhapur. 13.03.03 Earthwork - 16.918 km.C.D.
work-22 No.
Box cell/
Minor Bridge - 5No.
Major Bridge - nil

Position of Work of Widening of 3 Bridges on Amravati-Badnera Road

Sr.
No.
Name of Work Estimated cost (Rs. Lakh) Amount put to Tender Rs. in Lakhs Name of contractor Date of work order Position of work
1. Bridges on Amravati Badnera Road 370.00 64.99 M/s. Ideal Construction Co. Engineers Contractors, Nagpur. 17.01.05 Work completed.

Position of Work of Construction of Flyover Bridge

Sr.
No.
Name of Work Estimated cost (Rs. Lakh) Amount put to Tender Rs. in Lakhs Name of contractor Date of work order Position of work
1. Fly over bridge on Rajkamal and sham and Jaistambha Square Panchwati Square 1500.00 3181.00 M/s Gammon India Limited Mumbai 12.08.04 For Rajkamal flyover, 32 pile foundation out of 51 & 2 pier complete. Shutter work in progress and for Panchavati flyover, 18 slabs out of 35 complete, ramp work in progress.
MSRDC - Project - Amravati City Integrated Road Development
        Project
MSRDC - Project - Amravati City Integrated Road Development
        Project

Following Works will be tackled by M.S.R.D.C.

Sr.No. Name of Work Estimated Cost (Rs. Crore) Position
1. Railway Overbridge
Widening of Badnera ROB 10.00 The proposal for the GAD of Badnera rly bridge sent to Railway Department for approval.
2. Toll Booth 05.00 Proposal is submitted to Mumbai Office.