Name Of Work
|
Est. Cost
|
Bid Cost
|
Name of Contractor
|
Date of Starting
|
Date of Completion
|
Expenditure
|
Physical Progress
|
Construction of ROB on LC 90C
|
8.47 Crores
|
7.88 Crore
|
M/s Vijay Nirman Co.,Nagpur
|
30.7.04
|
15.8.06
|
5.37 Crore
|
Except Railway portion other works upto girder completed. Out of 16 deck slab 10
deck slab are completed
|
Construction of ROB on diversion road
|
3.17 Crore
|
3.05 Crore
|
M/s Vijay Nirman Co., Nagpur
|
19.8.04
|
31.5.06
|
0.96 Crore
|
Subway is completed Except Railway boundary 132 m 90% work is completed
|
Improvement to diversion road (7.2 km)
|
1.90 crore
|
1.59 + 0.78 = 2.37 Crore
|
M/s H.A. Vora
|
23.12.02
|
31.7.04
|
2.55 Crore
|
Completed
|
Improvement to internal roads (13.5 km)
|
Not Yet Started
|