Integrated Road Development Programme (IRDP) - Nanded

Works Required to be Transferred from P.W.D. tO MSRDC

Nature of work Cost/Amount in crores)
1 Eastern Bypass 25.00
2 Old Mondha bridge to Ambedkar chowk 1.00
3 Toll Plazas 3.50
Total 29.50

Holy Places Development Works to be Transferred to MSRDC

1 Kabranagar to MSH 2 Marg Khadakpura 9.50
2 ROB at Khadakpura 2.00
3 Major bridge on Godavari river at Khadakpura 7.00
4 Road work Marg (Sangat Saahed Part I) from old bridge to Naoghat bridge 2.50
Total 21.00

Works under Municipal Corporation to be Transferred to MSRDC

1 Road at Gokulnagar & Gorakhan to Deglur road to Chikhalwadi & flyover on Deglur road 4.00
2 MSH No.2 to Vasrani to Navaghat bridge and Naoghat bridge to dairy road (2.00 km * 18 m) 2.25
3 Kalamandir road to Khadakpura Ring road (2.00 km * 18 kms) 2.25
4 Kawatha road to Latur road (1.50 kms * 18 m) 1.70
5 Workshop road to Jangamwadi Dispensary upto western diversion road (1.20 kms * 18 m) 1.00
6 Construction of road behind the People's college from Yashvant nagar to Jangamwadi road 1.00
7 Road work from Chaitanyanagar to old Purnanagar via Tilaknagar (1.00 kms * 18 m) 1.00
8 Construction of road from Ashoknagar water tank to Hingoli road upto MGM college via Purbu - Han (2.30 kms * 18 m) 2.50
Total 15.70