| Sr. No. |
Location |
Activity |
Status |
Remarks |
| A |
Span between A1-P1 (Thane and CST side) |
|
|
|
| |
Foundations Substructure Superstructure |
Piling and pile caps . Pier, pier cap and bearing pecestals Fabrication of steel girders Expansion joint Wearing coat |
Completed Completed Completed Balance Balance |
Steel girder launching completed and desk slab completed |
| B |
Span between P1-P2 (Thane and CST side) |
|
|
|
| |
Foundations Substructure Superstructure |
Puling and pile cap Pier, pier cap and bearing pecestals Launching of PSC girders Deck slab RCC crash barrier and footpath parapet wall Expansion joint Wearing coat |
Completed Completed Completed Completed Completed Balance Balance |
Material is brought to site |
| C |
Span between P2-A2 (Thane and CST side) |
|
|
|
| |
Foundations Substructure Superstructure |
Piling and pile cap Abutment, pier and abutment/pier cap, bearing pedestals Deck slab (voided slab) RCC crash barrier and footpath parapet wall Expansion joint Wearing coat |
Completed Completed Completed Completed Balance Balance |
Material is brought to site |
| D |
Approaches (Thane and CST side) EEH side Powai side |
Road crust Pipe railing Footpath Road crust Pipe railing Footpath |
Top layer BC balance Completed 75% completed Balance Balance Balance |
In progress |